Xiong An First Assembly-type Building Less Than 42 Days Full Cap!

- Feb 02, 2018 -

On November 22, 2017, China Construction won the bid for the project of Xiong'an Citizens Service Center after strict bidding and publicity procedures. 

The project is the window of the Xiong'an New Area facing the whole country and even the world. It is the first appearance of the functional orientation and development concept of Xiong'an New District. In the beginning of reform and opening up to create "Shenzhen speed" of Chinese architecture, here has created a new "speed".


4 days to complete the installation of 3100 tons of basic steel.

5 days to complete the construction of the site temporary layout.

7 days to complete 120,000 cubic meters of earth excavation.                             

10 days completed 35,500 cubic meters of basic concrete pouring.

12 days completed on-site temporary office, build life.

25 days to complete 12,200 tons of steel components installed. 

40 days, a total of seven steel structure monomer cap. 

From start to fully capped only lasted 1000 hours!